17/04/2023
- Drone video of our site taken on 17 April 2023
24/02/2023
Continued:
- The installation of school furniture
- The M&E second fix to the ground floor classrooms
- Decoration to the ground floor classrooms
- The planting of shrubs and plants
- The installation of Kitchen items
- Floor finishes to the ground floor
- M&E progress in the plant room
- Carpentry works to the ground floor
- The installation of Smart Boards, Projectors etc
- The installation of bespoke furniture
20/02/2023
Continued:
- The installation of lights to the main hall
- The M&E second fix to the ground floor classrooms
- Decoration to the ground floor classrooms
- The installation of external fencing
- Floor finishes to the ground floor
- M&E progress in the plant room
- Groundworks – Installing kerbs, edgings and block paving
- Began bringing the furniture into the building
- The installation of tarmac to the front
- Commissioning and balancing of M&E systems
- The decoration to both floors
10/02/2023
Continued:
- The installation of lights to the main hall
- The M&E second fix to the ground floor classrooms
- Decoration to the ground floor classrooms
- The installation of external fencing
- Floor finishes to the ground floor
- M&E progress in the plant room
- Groundworks – Installing kerbs, edgings and block paving
- The installation of bespoke furniture
- The installation of tarmac to the front
- The ground floor second fix to the misting system
- Commissioning and balancing of M&E systems
03/02/2023
Continued:
- The installation of lights to the main hall
- The M&E second fix to the ground floor classrooms
- The installation of mirrors to the WCs and hygiene room
- Decoration to the ground floor classrooms
- The installation of external fencing
- Floor finishes to the ground floor
- M&E progress in the plant room
- Groundworks – Installing kerbs, edgings and block paving
- The installation of bespoke furniture
27/01/2023
Continued:
- The grid ceiling to the ground floor corridor and main hall
- The M&E second fix on the ground floor
- Installation of the play top equipment
- The installation of IPS panelling to the ground floor
- Decoration to the ground floor classrooms
- The installation of external fencing
- Floor finishes to the ground floor
- M&E progress in the plant room
- Groundworks – Installing kerbs, edgings and block paving
20/01/2023
Continued:
- The grid ceiling to the ground floor corridor
- The Installation of classroom lights and ceiling tiles to the ground floor
- The M&E second fix on the ground floor
- The cladding to the front elevation
- Installation of the handrail and glass to stairwell 1
- Air sealing and fire stopping works
- The installation of toilets and IPS panelling to the ground floor
- Decoration to the ground floor classrooms
- Floor finishes to the first floor
- M&E progress in the plant room
- Groundworks – Installing kerbs and edgings
13/01/2023
Continued:
- The grid ceiling to the ground floor classrooms and first floor corridor
- The Installation of classroom lights
- Plastering works to the entrance lobby
- The M&E first fix on the ground floor
- The cladding to the front elevation
- Installation of the handrail to stairwell
- Air sealing and fire stopping works
- Decoration to the ground floor classrooms
- Floor finishes to the first floor
- M&E progress in the plant room
- General ground works
06/01/2023
Continued:
- The grid ceiling to the ground floor classrooms
- The Installation of classroom lights
- Plastering works to the stairwells
- The M&E first fix on the ground floor
- The cladding to the front elevation
- Air sealing and fire stopping works
- Decoration to the ground floor classrooms
- Works to the balcony
- M&E progress in the plant room
- General ground works
23/12/2022
Continued:
- The grid ceiling to the ground floor classrooms and first floor corridor
- The White rock to the hyenine room and other areas
- Plastering works to the ground floor corridor
- The installation of the lift
- The M&E first fix on the ground and first floor
- The cladding to the front elevation
- Air sealing and fire stopping works
- Decoration to the ground floor classrooms
- Tarmacking to the rear of the building
- Screed to the hall
- M&E progress in the plant room
09/12/2022
Continued:
- The grid ceiling to the first floor and main hall
- Plastering works on the first and ground floor
- The M&E first fix on the ground and first floor
- The boarding and to the ground floor
- Dot and dabbing on the ground and first floor
- The cladding to the front and rear elevation
- The decorating works to the main hall, ground floor and the first floor
- Mist coating to the ground floor classrooms
- M&E progress in the plant room
- The installation of the radiators on both floors
- Continued carpentry works on both floors
- Groundworkers grading the field side in preparation for tarmac
Next week will see us continue with the above; begin installation of the lift and bring the screeders back for the hall
02/12/2022
Continued:
- The grid ceiling to the first-floor classrooms
- The installation of the curtain wall
- Plastering works in the first and ground floor classrooms and main hall
- The M&E first fix on the ground and first floor
- The boarding and metal partitions to the ground floor
- Dot and dabbing on the ground and first floor
- The cladding to the front and rear elevation
- Air sealing and fire stopping works
- The decorating works to the main hall, ground floor and the first floor
- Mist coating to the ground floor classrooms
- M&E progress in the plant room
- The installation of the sinks into the WCs
- Continued installing door frames, doors and glass in the admin/staff areas
25/11/2022
Continued:
- The grid ceiling to the first floor classrooms
- The installation of the balcony door
- Plastering works in the first and ground floor classrooms, staff room toilets and admin area
- The M&E first fix on the ground and first floor
- The boarding and metal partitions to the ground floor
- Dot and dabbing on the ground and first floor
- The cladding to the front and rear elevation
- Air sealing and fire stopping works
- Mist coating to the ground floor classrooms
- M&E progress in the plant room
11/11/2022
Continued:
- Continued plastering works in the first and ground floor classrooms, staff room toilets and admin area
- The M&E first fix has continued on the ground and first floor
- Boarding and metal partitions to the ground floor and have continued the breakout areas, staff offices/meeting room on the first floor and lift shaft
- Dot and dabbing on the ground and first floor
- The cladding to the rear elevation
- Air sealing and fire stopping works
- Misting systems on the ground floor
- Mist coating to the ground floor classrooms
- Continued M&E progress in the plant room
- Continued MF ceilings on the first floor
- Continued plastering the MF ceilings on the first floor
This week we also began screeding the ground floor classrooms and practical areas.
This week will see us continue with the above and begin screeding the ground floor and began installing the BMS wiring.
07/11/2022
Continued:
- Continued plastering works in the first and ground floor classrooms, staff room toilets and admin area
- The M&E first fix has continued on the ground and first floor
- Boarding and metal partitions to the ground floor and have continued the breakout areas, staff offices/meeting room on the first floor and lift shaft
- Dot and dabbing on the ground and first floor
- The cladding to the rear elevation
- Air sealing and fire stopping works
- The drainage and curbing works to the field side
- Misting systems on the ground floor
- Mist coating to the ground floor classrooms
- IPS systems to the ground floor toilets
- Continued M&E progress in the plant room
- Fire alarm works
This week we also began installing the doors and glass on the first floor, began installing skirting and kitchen units to the first floor, began MF Ceiling works on the first floor, and plastered one of the stairs ready for mist coating and concreted the bin store and heat pump area.
This week will see us continue with the above and begin screeding the ground floor
28/10/2022
Continued:
- Continued plastering works in the first and ground floor classrooms, staff room toilets and first floor hallway
- The M&E first fix has continued on the ground and first floor
- Boarding and metal partitions to the ground floor and have began the breakout areas and staff offices/meeting room on the first floor
- Dot and dabbing on the ground floor
- The cladding to the rear elevation
- Air sealing works
- The drainage and curbing works to the field side
- Misting systems on both floors
This week we also began works in the plant room, began painting misting coats in both floors classrooms and began installing the IPS systems in the first floor toilets,
Next week will see us continue with the above and begin the IPS on the ground floor
21/10/2022
Continued:
- Continued plastering the first-floor classrooms and ground floor toilets
- The M&E first fix has continued on the ground and first floor
- Boarding and metal partitions to the ground floor and boarding to the first floor classrooms and toilets
- Dot and dabbing in the reception toilets and both floors’ classrooms
- The cladding to the field side, and admin side
- The installation of window frames and glass on the ground floor
- Air sealing works
- Lightning protection works
- The drainage works to the field side
This week we also painted the plant room floor, began installing the external doors, began installing the misting systems to the first floor, constructing the curbs and flat stone to the field side.
Next week will see us continue with the above, begin installing the IPS systems in the year 6 classrooms.
14/10/2022
Continued:
- Boarding on the first and ground floor
- Roof works to the field side, hall and admin area
- The M&E first fix has continued the ground floor and first floor
- The partition works on the first and ground floor
- The install of the window frames and glass on the ground floor
- Continued taping and jointing the partitions
- The air sealing works
- Dabbing the first floor
- Installing the bulk heads
- The ducting works
This week we also screeded the wet areas on the ground floor, and painted a mist coat on the plant room walls.
07/10/2022
Continued:
- Boarding on the first and ground floor
- the roof works field side roof
- the M&E first fix has continued the ground floor and first floor
- the partition works in the admin area and below the field side roof
- Installing the services into the plant room
- The partition works for the kitchen
- The install of the window frames and glass on the ground floor
- Continued taping and jointing the partitions
- The air sealing works
This week we also began dot and dabbing on the first floor,
Next week will see us continue with the above, and begin screeding the wet areas on the ground floor,
03/10/2022
Continued:
- Boarding on the first and ground floor
- the roof works on the admin, hall, and field side
- the M&E first fix has continued the ground floor and first floor
- the partition works in the admin area and below the field side roof
- Installing the services into the plant room
- The partition works for the kitchen
- The install of the window frames on the ground floor
- Continued taping and jointing the partitions
- The air sealing works
This week we have also began; the construction and concrete pour of the air-source heat pump and misting system tank area, installed the windcatchers to the admin area roof, and we have dropped the field side scaffold and loading bay.
23/09/2022
Continued:
- Boarding on the first and ground floor
- the roof works on the admin, hall, and field side
- the M&E first fix has continued the ground floor and first floor
- the partition works in the admin area and below the field side roof
- Digging and backfilling the service trenches in the main yard and near the site entrance
- Installing the services into the plant room
- The partition works for the kitchen
This week we have also began; the install of the window frames on the ground floor field side, the install of the single ply membrane on the balcony, installing the door linings on the first floor and we began plastering the plant room,
Next week will see us continue with the above, drop the field side scaffold, bring in a crane for the continued mechanical works
09/09/2022
Continued:
- The first fix on the ground floor
- The metal stud on the first floor
- the roof works on the admin roof, hall roof and field side roof
- the M&E first fix has continued on the ground floor
- installing ducts to both the ground floor and the first floor
- Boarding the first floor
- The metal stud partitions on the first floor
- The metal stud partitions in the admin area
- Containment works for the first floor electrical
- The air sealing works
- Digging the service trenches in the main yard and near the site entrance
- Installing the services
- The partition works for the kitchen
- Installing the top sheets and insulation to the admin/lower roof
We have completed, the installation of the top sheets and insulation of the hall roof and field side roof,
Next week will see us continue with the above, begin installing the solar panels on the field side, and welcome another site manager to the team; Marlon Butt
05/09/2022
Continued:
- The first fix on the ground floor
- The metal stud on the first floor
- the roof works on the admin roof, hall roof and field side roof
- the M&E first fix has continued on the ground floor
- installing ducts to both the ground floor and the first floor
- Boarding the first floor
- The metal stud partitions on the first floor
- The metal stud partitions in the admin area
- Containment works for the first floor electrical
- The air sealing works
And we have begun:
- Digging the service trenches in the main yard
- Installing the services
- Filling the gaps in the masonry left out for the netters
- The partition works for the kitchen
- Installing the top sheets and insulation on the field side roof and hall roof
Next week will see us continue with the above and begin installing the solar panels on the field side.
26/08/2022
Continued:
- The first fix on the ground floor
- The metal stud on the first floor
- the roof works on the admin roof, hall roof and field side roof have commenced
- the M&E firs fix has continued on the ground floor
- installing ducts to both the ground floor and the first floor
And we have begun:
- Boarding the plant room
- Boarding the first floor
- The metal stud partitions in the admin area
- The drainage on the field side of the building
- Containment works for the first floor electrical
- The air sealing works
Next week will see us continue with the above and bring back the bricklayers to begin filling in the gaps left out for the netters, and continue in our preparations for students and staff returning in September.
19/08/2022
Continued:
- The scaffold strip
- Boarding to the ground floor
- Progressing the partition works on the first floor
- The first fix works on the ground floor
- The installation of the ducts
- Continued the drainage works
We have begun:
- The construction of both the hall side roof and the field side roof
Next week will see us continue with the above and begin air sealing works.
05/08/2022
Since we last issued progress photos we have; continued with the scaffold strip, continued boarding the ground floor, continued installing the windows on the ground floor, continued with the M&E containment and chasing works on the ground floor, we have begun boarding the first-floor steels, begun and finished the netting for the hall and admin prior to commencing the roof liner sheets. We have also commenced some drainage diversion works between the two existing buildings.
Next week will see another crane on-site installing the roof liner sheets and continuing with the above works.
22/07/2022
Since we last issued progress photos the masonry and scaffold works have continued, began installing the soleplate on the first floor, continued the installation of the windows to the first floor, commenced the M&E containment works, continued with the installation of the facias, soffits and guttering to the main block.
Next week will see us continue with the above, begin the partition works on the first floor and begin installing the windows on the ground floor.
15/07/2022
We have continued with installing the window frames on the first floor, continued with the construction of the partition walls along the ground-floor, the scaffolding and masonry works have continued, we have continued installing the containment works for the electrical works, began the wall chasing in the main block, and we have installed another external wall out of the structural framing system.
Next week will see us continue with all the above, begin taking down the main roof edge protection and netting and begin the construction of the hall roof.
01/07/2022
Since we last issued our progress photos, we have commenced the intumescent paint to the steels supporting the first floor, commenced the fire encasement to ground floor beams, began installing the window frames to the first floor, installed the SFS to the hall roof and the brickwork and scaffold have progressed further.
Next week will see us continue with all the above, begin installing the facias, guttering and downpipes and continue with the removal of the main roof edge protection.
20/05/2022
The blockwork and Bradstone has progressed up to and beyond the first-floor level on the main block and the masonry is up to eaves level on the field facing lower roof area. The masonry to the admin, plant room and hall area is constructed up to the first lift. The optima lintels have been installed above the Ground floor windows.
Moving into the next two weeks we will be continuing with the masonry works up to roof level on the main block, the scaffolding will progress, the steel erectors will be installing steels at first floor level and around the hall parapet. The SFS systems to the first-floor main block and around the hall parapets will continue. The windows will be delivered and the steel fire protection works will commence.
6/05/2022
We have poured the concrete to the first-floor slab, installed the first lift of scaffold around the two-story section of the building.
The blockwork and the bradstone is continuing to progress. Next week will see us continue with the masonry, continue the scaffold installation, and begin intumescent painting to the steels.
22/04/2022
We have installed the first-floor metal decking, began installing the roof sheets and preparing for the top sheets. The blockwork is progressing, and we have also commenced the bradstone to the main block. Next week will see us lay the reinforcements to the first floor and pour the concrete, as well as continue the first lift of scaffolding.
29/03/2022
Bird’s eye view of the building work progress
25/02/2022
This week we have completed the stormwater drainage. We have also installed a temporary ramp to the infant School and extended the artificial grass area as well as completing the substructure masonry. Next week will see us install the precast concrete planks and continue with the foul drainage.
13/1/2022
Building Work Schedule:
January
- Concrete delivery for foundations.
- Masonry (Block) deliveries commence
February
- w/c 31st Jan Precast ground floor installation commences
- w/c 14th February – Steel frame installation commences.
March
- Installation of first floor metal deck flooring.
- Concrete topping of the first floor
- Masonry works ongoing
April
- Masonry works and deliveries ongoing.
- Roofing deliveries and installation commence – approx.
22/11/2021
The new school will replace the existing building at the Cheltenham school with work starting on Monday, 22 November.
The ceremony, on Thursday, 11 November, was attended by Cllr Philip Robinson, Cabinet member for Economy, Education and Skills at Gloucestershire County Council, Cllr Emma Nelson, representatives of Warden Hill Primary School and the Gloucestershire County Council framework contractors, E G Carter & Co Ltd who are delivering the new school.